Roads and Highways Department
Profile
- Head
- —
- Role
- Chief Engineer
- Annual budget
- —
- Staff
- 9331
- Established
- 1962
- Legal basis
- The Highways Act, 1925 (primary statute governing national highways); established by government notification in 1962 splitting the colonial-era Construction & Building organisation into Roads and Highways Department and Public Works Department; operates under the Rules of Business 1996.
Managing a Tk 32,329 crore ADP portfolio (FY2025-26, via parent RTHD) with three flagship corridors in contention: (1) Dhaka-Chittagong N1 corridor 10-lane expansion ($5.5 billion, ADB financing talks active); (2) Dhaka-Ashulia Elevated Expressway (58% complete, deadline slipping past July 2026); (3) BRT Line-3 Dhaka-Gazipur (97% complete, lane-separation design abandoned, fate with new government). Dhaka Bypass Expressway (first 18 km) opened August 2025 -- implemented under PPP outside RHD's direct ADP envelope. TIB's October 2024 audit exposed systemic procurement corruption (23-40% loss rate) with no formal RHD response or reform circular issued as of verification date.
Recent activity
- 2026-02-17 other With Tarique Rahman's BNP government sworn in on 17 February 2026, Minister Shaikh Rabiul Alam directed RHD officials to fast-track stalled bridge and road projects and prioritise maintenance of the Dhaka-Chittagong corridor (N1 highway), signalling renewed political attention to RHD's project pipeline. ↗↗
- 2026-02-22 reform Minister Rabiul Alam ordered RHD to accelerate stalled highway and bridge projects; directed particular focus on the Dhaka-Chittagong N1 corridor where RHD has finalised a 10-lane expansion plan (estimated $5.5 billion) including a 13.5 km elevated section at Jatrabari-Madanpur and an 8 km elevated section at Salimpur-Sagarika, Chattogram; Asian Development Bank has engaged on financing options. ↗↗↗
- 2026-03-01 audit Transparency International Bangladesh's October 2024 governance report on RHD -- based on 73 key informant interviews and 13 group discussions from July 2023 to September 2024 -- estimated that 23-40% of RHD construction contract values (Tk 29,230 crore to Tk 50,835 crore over the 15-year period FY2009-10 to FY2023-24) were lost to corruption through bribery, tender manipulation, work-order sales, and political extortion. The top 15 contracting firms captured 72% of e-GP work orders (~Tk 57,000 crore) over a decade via collusive procurement. ↗↗↗↗
- 2026-04-28 other BRT Line-3 (Dhaka airport to Gazipur, 20.5 km northern section) remains in limbo: RHD's construction responsibility (16 km of road, 6 flyovers, 25 BRT stations, 2 terminals) is 97.69% complete, but the project has been effectively shelved without dedicated bus lanes after Tk 2,800+ crore expenditure over 13 years (since 2012 inception); total cost overrun stands at 223% of the original Tk 2,039.84 crore estimate. Interim BRTC bus service on the shared corridor launched December 2024. The new BNP government has not announced a decision on restoring lane-separation as originally designed. ↗↗↗
- 2026-05-11 other Dhaka-Ashulia Elevated Expressway (24 km, Tk 17,553.04 crore, China Exim Bank loan of Tk 9,692 crore, contractor CMC): physical progress reached approximately 58% as of 11 May 2026 against a July 2026 completion deadline, placing it significantly behind schedule. Key bottlenecks include unresolved land handover from Civil Aviation Authority at Kawla near Hazrat Shahjalal Airport and incomplete utility relocation. RHD is the implementing agency under the project director. ↗↗↗
Provenance & notes
RHD established in 1962 when the colonial-era Construction & Building organisation was split into RHD and Public Works Department. Road network figures from the official RHD website: 20,866.36 km as of the most recent AtGlance page (up from 2,500 km at establishment). Sanctioned staff: 9,331 posts (573 Class I, 773 Class II, 4,759 Class III, 3,226 Class IV) per RHD Overview page; the 9,369 figure cited in some secondary sources appears to be a slightly older snapshot. current_head set to null: AKM Manir Hossain Pathan was confirmed as Chief Engineer in February 2022 (Financial Express, Dhaka Tribune); a subsequent appointment (Ishaque) was reported in December 2022; further reshuffles likely followed the August 2024 interim government and the February 2026 BNP election; the RHD chief engineer profile page (https://www.rhd.gov.bd/VVIPProfile/chiefengineer.asp) was not accessible in search results, and no 2025-2026 appointment announcement was found in public media at verification date. Reporting agents should check rhd.gov.bd directly before populating this field. annual_budget_bdt omitted: RHD's standalone ADP allocation is not disaggregated from the RTHD Tk 32,329.57 crore envelope in publicly accessible budget documents; the parent file (road-transport-and-highways-division.json) carries the division-level figure. TIB 2024 report: executive summary PDF published October 2024 at ti-bangladesh.org; figure range Tk 29,230-50,835 crore represents low-end and high-end corruption loss estimates over FY2009-10 to FY2023-24; 23-40% corruption rate applies to total RHD construction contract values. BRT Line-3: ADB and AFD jointly financed; original cost Tk 2,039.84 crore in 2012; current estimate Tk 6,597.32 crore (4th revision proposed, 223% overrun); physical completion 97.69% for RHD scope (16 km road + 6 flyovers + 25 stations + 2 terminals). Dhaka-Ashulia Elevated Expressway: Tk 17,553.04 crore; China Exim Bank loan Tk 9,692 crore; contractor China National Machinery Export Import Corporation (CMC); 58% complete per TBS report of 11 May 2026. Dhaka Bypass Expressway: implemented under PPP by Sichuan Road & Bridge (Group) Co. Ltd; 48 km total; first 18 km (Bhogra Bypass, Gazipur to Madanpur) inaugurated 24-25 August 2025. Verification based on 2+ primary sources for all material claims.
Sources
- https://en.wikipedia.org/wiki/Roads_and_Highways_Department
- https://www.rhd.gov.bd/RHDAtGlance/index.asp
- https://www.rhd.gov.bd/OverviewOfRHD/Default.asp
- https://www.rhd.gov.bd/Strategy/RHD/View.asp
- https://www.ti-bangladesh.org/images/2024/report/RHD/Executive-Summary-RHD-Governance-Challenges-en.pdf
- https://www.thedailystar.net/news/bangladesh/news/roads-and-highways-projects-tk-50835cr-lost-graft-15yrs-3723626
- https://en.prothomalo.com/bangladesh/z7xt4wnqbg
- https://www.bssnews.net/news-flash/215340
- https://www.tbsnews.net/bangladesh/infrastructure/dhaka-ctg-corridor-10-lane-highway-or-fully-elevated-1416971
- https://www.adb.org/projects/45174-001/main
- https://www.newagebd.net/post/country/282935/first-ever-bus-rapid-transit-line-project-may-end-without-dedicated-bus-lanes
- https://www.thedailystar.net/news/bangladesh/transport/news/dhaka-gazipur-brt-shelved-after-spending-tk-2800cr-13yrs-4008491
- https://en.wikipedia.org/wiki/Dhaka_BRT
- https://www.daily-sun.com/post/788879
- https://en.wikipedia.org/wiki/Dhaka%E2%80%93Ashulia_Elevated_Expressway
- https://english.news.cn/20250825/e14bc4cc765749d49ac138eb4638fa35/c.html
- https://www.dhakatribune.com/bangladesh/383170/dhaka-bypass-expressway-opens-toll-free-for-eid
- https://en.wikipedia.org/wiki/Dhaka_Bypass_Expressway
- https://www.bssnews.net/news/362326
- https://eservices.rthd.gov.bd/foreign_project.php
- https://today.thefinancialexpress.com.bd/stock-corporate/manir-hossain-new-rhd-chief-engineer-1644680413
- https://www.dhakatribune.com/bangladesh/287151/monir-hossain-appointed-chief-engineer-of-rhd