← Government Watch

Dhaka Transport Coordination Authority

autonomous · verified (verified 2026-05-17)

Profile

Head
Neelima Akhter
Role
Executive Director
Annual budget
Staff
Established
2012
Legal basis
Dhaka Transport Coordination Authority Act, 2012; traces institutional origins to the Dhaka Transport Coordination Board established 1998 under the Dhaka Urban Transport Project (DUTP).

DTCA is advancing three interlocked but stalled agendas: (1) the 42-route bus franchise rollout -- launched on a single Green Cluster pilot route in February 2026 after owner resistance reduced the initial scope from eight simultaneous routes -- with a new Route Franchise Act pending ministry approval; (2) the 400-electric-bus programme under the World Bank Bangladesh Clean Air Project ($290 million WB loan, Tk 671 crore DTCA Transport Fund, AssetCo ownership model) with ECNEC approval expected imminently but bus procurement deferred to 2027-2030; and (3) BRT Line 3 effectively abandoned after Tk 2,800 crore and 13 years, with the corridor open to mixed traffic using BRTC standard diesel buses. Metro coordination (MRT Line 6 Rapid Pass integration, feeder bus planning for MRT extensions) continues alongside an ADB-financed update of the Revised Strategic Transport Plan, whose final draft proposes three suburban low-cost BRT corridors and expanded MRT Lines 1, 5, and 6 up to 2045.

Recent activity

Provenance & notes

DTCA was formally established September 2, 2012 under the Dhaka Transport Coordination Authority Act, 2012; its institutional predecessor was the Dhaka Transport Coordination Board (DTCB), established 1998 under the Dhaka Urban Transport Project. Under the DTCA Act 2012, the Minister of Road Transport and Bridges serves as ex officio Chairman; since February 17, 2026 that is Sheikh Rabiul Alam (BNP). The Executive Director (Additional Secretary rank) is the chief executive; Neelima Akhter (also spelled Nilima Akhter in some sources) has held this role at least since mid-2024, confirmed by the January 1, 2026 bus reform workshop and the Rapid Pass Hatirjheel launch. head_since omitted: exact appointment date not found in public records. staff_count omitted: no verified primary-source figure for sanctioned posts found; April 2026 job circular adds 23 temporary posts but total org size is not disclosed in accessible sources. annual_budget_bdt omitted: DTCA does not publish a standalone operating budget; its major capital activities are embedded in RTHD's ADP. BRT Line 3 shelving: the interim government (post-August 8, 2024) made the effective decision not to proceed with BRT operations; the 6th extension to December 2026 is for civil works only. World Bank Clean Air Project (P502572): WB board approved June 18, 2025 ($290 million IDA credit); total project cost $355 million; DTCA is lead implementing agency for the bus component. Transport Fund structure: Tk 427 crore capitalisation + Tk 244 crore seed capital; AssetCo (state-owned) procures and owns buses; DTCA pays operators fixed fees; fare revenue and demand risk sit with government. RSTP update: ADB KSTA 54451-001 funded the revision; final draft submitted to government; proposes three suburban low-cost BRT lines and MRT expansion to 2045, rules out new MRT corridors not already under construction. Verification: 2+ primary sources cross-checked for all material claims.

Sources